Time to Pour Walls!
Well the guy I had lined up to do the forms was too busy. I called someone else on Tuesday night, and they had a crew out Wednesday and they formed up the walls and poured cement! WOW, now thats service!!
 
Rebar to tie exisiting building to new building


 
Unloading the Forms


 
Forms are all set, only took 4 hours wow!



 
I ran my return piping right inside the forms, COOL!


 
Pumper Truck and Cement Truck are ready to go.


 
Sure beats using a wheelborrow to get the cement back there.


 
Starting to pump cement around 2pm. I troweled the cement in filter pit and around the bottom drain piping, the crew took care of the walls. They finished around 4:30pm. 13 yards of Cement total.




 
One of the guys was there 7am this morning stripping the forms off. I helped him. A half hour later all the forms were off. The truck came and the guys were all loaded and out of there by 8am WOW.




 
The little box I made to hold my plumbing worked out great!


 
I put drainage tile line all round the foundation and 3800 pounds of rock. This will keep any groundwater drained away from the building.